Existing four-span timber bridge over Long Creek near Torquay, Saskatchewan

Case study

Torquay Bridge Replacement & Road Realignment

Grid Road 707 over Long Creek, near Torquay, Saskatchewan

InfrastructureStructuralConstruction Services

For almost 70 years, a four-span timber bridge built in 1957 carried Grid Road 707 over Long Creek, about 7 km southwest of Torquay. When it was time to replace it, the Rural Municipality of Cambria No. 6 brought Sevana on as prime consultant. We're replacing it with a 30 m precast concrete bridge and straightening out the road that leads onto it. Construction starts in January 2027, and we're with the RM from the first site visit to the final handover.

Project facts

  • Services Hydraulic and structural design, road realignment, permitting, tender and contract administration
  • Sector Municipal infrastructure; transportation

Challenge

The old bridge was showing its age. Its timber piles were rotting and splitting, the embankments were eroding, and drivers came onto the bridge around a tight curve. The new crossing had a few hurdles of its own. The road meets the creek at a sharp 45° angle, which standard precast parts aren't detailed for. The ground under the site is wet, loose sand that kept causing the test holes to cave in. Long Creek is a fish-bearing stream with strict timing for in-water work. And because this is the only crossing on Grid Road 707, the road had to stay open while the new bridge is built.

Scope

We started by getting to know the creek. We walked the site, built a hydraulic model of Long Creek, and used it to size the new bridge so it clears the 1-in-50-year flood with room to spare. From there we designed a two-span, 9.8 m-wide precast concrete bridge. We adapted the Ministry of Highways standard caps to fit the 45° skew, and we specified driven steel pipe piles that can handle the soft, sandy ground. We also redesigned about 260 m of the road to take out the curve, and we secured the provincial and federal fish-habitat approvals before the project went to tender.

We put together the tender package and helped the RM choose a contractor, and Harbuilt Construction Ltd. was awarded the work. Now we're administering the contract for the RM. We're reviewing submittals and handling extra work and progress payments, and we'll be on site for key milestones like pile driving and girder placement. Our as-built drawings and handover report will close the project out.

Result

The new bridge will be built right beside the old one over the winter, so traffic can keep using the old bridge the whole time. Once the new bridge is finished in spring 2027, the road will switch over to the new alignment and the old timber bridge will be removed. When it's done, the RM will have a longer, wider concrete crossing that lines up with the creek and is built for today's flows and loads, with a safer, smoother approach. Final completion is scheduled for July 2027.

Project facts

  • Services Hydraulic and structural design, road realignment, permitting, tender and contract administration
  • Sector Municipal infrastructure; transportation

Contact

Have a project in mind?
Contact us today.

Tell us about your project and you'll hear back from the engineer who will do the work.

Stay connected

Follow Sevana for project updates, engineering insights and team news.