Case study
Jedburgh & Township Road 275 Bridge Replacements
RM of Orkney No. 244, near Yorkton, Saskatchewan
The RM of Orkney No. 244 had two old timber bridges that were ready to retire: the two-span Jedburgh Bridge and the three-span Township Road 275 Bridge over Yorkton Creek. Working with Resource Management International Inc. (RMI), Sevana designed two wider, single-span precast concrete bridges to replace them. The new crossings are a 12 m span at Jedburgh and an 18 m span at Township Road 275. We stayed with the project from design and tender all the way through to the record drawings.
Project facts
- Services Structural design, tender documents and construction support
- Sector Municipal infrastructure; transportation
Challenge
Both timber bridges were only 7.3 m wide, and their piers stood right in the creek. The new bridges needed to be wider and clear the water completely. They also had to go in without getting in the way of local farmers during seeding and harvest, and without any in-water work during the spring fish window. On top of that, the project had started out as an arch culvert, so the existing geotechnical work wasn't written with a bridge in mind. And the piles went in during December and February, into frozen ground.
Scope
As structural Engineer-of-Record, working under RMI, we designed both bridges using proven Saskatchewan Ministry of Highways standard components: precast prestressed concrete stringers, precast abutment caps and steel bridgerail. We worked out the steel pipe pile foundations from the existing borehole data, and we combined both bridges into a single tender so one contractor could handle both sites in one trip.
Once construction got going, we reviewed submittals and RFIs, and were on site for pile driving, girder erection and the final walkthrough. When a few of the winter piles ended up slightly out of position, we checked them and confirmed no repairs were needed. We wrapped things up with the final quantities, record drawings and the ICIP funding declaration.
Result
Minty's Moving Ltd. built both bridges over the 2024–25 winter, and they opened to traffic on March 6, 2025. Each crossing is now 8.5 m wide, 1.2 m wider than before, and the single-span design removed all three piers from the creek. Local and farm traffic now has two reliable, full-width crossings built for modern highway loads.
Project facts
- Services Structural design, tender documents and construction support
- Sector Municipal infrastructure; transportation


Contact
Have a project in mind?
Contact us today.
Tell us about your project and you'll hear back from the engineer who will do the work.
Stay connected
Follow Sevana for project updates, engineering insights and team news.