The new 49 m steel girder bridge on Highway 955 over the Clearwater River, about 63 km north of La Loche, Saskatchewan

Case study

Highway 955 Bridge Replacement, Clearwater River

About 63 km north of La Loche, Saskatchewan

InfrastructureConstruction Management

The Saskatchewan Ministry of Highways replaced the 1970s steel truss bridge on Highway 955 over the Clearwater River, about 63 km north of La Loche in Clearwater River Provincial Park. The deteriorated, single-lane, roughly 5 m-wide truss was the only crossing on a route used by local residents, the Clearwater River Dene Nation, park visitors and mining traffic. The new 49 m single-span weathering steel girder bridge, with an 8.5 m driving width, sits on 610 mm steel pipe piles socketed into bedrock. Stantec Consulting Ltd. led construction administration, with Sevana as Project Manager. Warman Construction Ltd. built a temporary detour bridge, demolished the truss and built the new bridge between May and October 2026. The new bridge opened in October 2026.

Project facts

  • Services Construction project management
  • Sector Provincial highway

Challenge

The existing crossing was a deteriorating, single-lane steel truss built in 1973–74, and the only highway access north of La Loche. It had to be replaced without cutting off residents, the Clearwater River Dene Nation, park visitors or mining traffic, and the work sat inside Clearwater River Provincial Park under Transport Canada, DFO and Saskatchewan Parks conditions. Once construction was underway, the bedrock — gneiss with quartz veins — proved harder than expected, which changed the piling and put pressure on the schedule.

Scope

Sevana served as Project Manager, named key personnel, under a subconsultant agreement with Stantec, and as backup Second Level Supervisor. We ran the bi-weekly progress meetings and were the main day-to-day link between Warman Construction, the Ministry and Stantec's site team. We tracked submittals and RFIs, progress estimates and site occupancy, and managed changes including a supplemental agreement that widened the temporary detour to a 5.4 m travelled way so mining traffic could keep moving. We are also completing the project close-out.

Result

The new 49 m girder bridge opened in October 2026, replacing the single-lane truss with an 8.5 m-wide crossing. A temporary detour, widened to a 5.4 m travelled way, kept mine and community traffic moving for the duration of the work.

Project facts

  • Services Construction project management
  • Sector Provincial highway

Contact

Have a project in mind?
Contact us today.

Tell us about your project and you'll hear back from the engineer who will do the work.

Stay connected

Follow Sevana for project updates, engineering insights and team news.